What utility co-ordination means on a highways scheme

Utility co-ordination is the discipline of finding, understanding and managing everything buried beneath the carriageway before, during and after the works. On a UK highway scheme that means dealing with the statutory undertakers, working within the New Roads and Street Works Act (NRSWA) framework, and coordinating record requests, trial holes, diversions and works liaison so the main scheme is not held up.

It is one of the single biggest causes of programme slip and cost overrun on highway schemes, and it is almost always avoidable when it is planned properly and started early.

Why the programme slips when it is left late

Every experienced highways PM has been through it. The scheme is designed, priced and programmed on the assumption that the utilities can be worked around. Then the tarmac comes off, a service is found where the records said nothing was there, and the whole programme takes a step back while diversions are designed, priced, permitted and installed.

The specific causes are consistent scheme to scheme:

  • BT and Openreach diversion lead times commonly run to sixteen weeks or more from application to install
  • Gas main relocations can require National Grid design, permit and installation windows that dwarf the main works
  • High voltage cable diversions need coordinated shutdowns, often booked months in advance
  • Statutory undertaker records are frequently out of date or contradict each other, and only site trace resolves the truth

What Arete does

Arete runs utility co-ordination as a single, joined-up workstream, from the first record request to the final as-built.

  • Full desk study using C2, C3 and C4 utility records from every relevant undertaker
  • Reconciliation of contradictory records and identification of the trials needed to close them out
  • Specification and management of trial holes and non-intrusive utility survey
  • Diversion feasibility and cost estimating, benchmarked against realistic undertaker lead times
  • Statutory undertaker liaison and application management, including the C4 works stage
  • On-site coordination during construction, including permit management and diversion sequencing

What you get

Every engagement produces the same set of tangible deliverables so the client always has a clear record of what was reviewed, agreed and reported.

  • Utility desk study report with reconciled C2 and C3 records
  • Trial hole specification, results and interpretation
  • Diversion cost estimate with realistic programme dates
  • Undertaker liaison log and application status tracker
  • Combined services drawing overlaid on the scheme design
  • On-site coordination report during construction, if required

When to bring us in

The value of this service compounds the earlier you appoint. As a rule, get in touch if any of the following apply:

  • The scheme sits over any significant buried services, especially in an urban or historic area
  • You have record drawings that appear to disagree with each other
  • The programme depends on a fixed handover date that cannot slip
  • A diversion is likely to be needed but nobody has priced it yet
  • You are entering an ECI or two-stage tender and need utility risk quantified up front

Sector focus

Arete works almost exclusively with local authorities and public bodies on highways and infrastructure schemes across Cambridgeshire and the East of England. That focus means every recommendation is calibrated to the standards, procurement routes and reporting cadences public sector clients need.

Frequently asked questions

What is a C2, C3 and C4 in utility works?

These are the standard NRSWA record request stages. A C2 is a preliminary enquiry to a statutory undertaker for the presence of apparatus. A C3 is a detailed request for the design of works needed to accommodate a scheme. A C4 is the formal notice to carry out those works, with associated cost apportionment.

Who pays for utility diversions?

The answer depends on who is promoting the scheme, the age and location of the apparatus and the terms under which it was originally laid. On many highway schemes the New Roads and Street Works Act splits the cost between the scheme promoter and the undertaker on a defined basis. Arete estimates the apportionment as part of the diversion cost work.

How long does a BT or Openreach diversion take?

As a rule of thumb, sixteen weeks from application to complete install is a realistic minimum for a straightforward BT diversion in an urban area. Complex or high-value diversions can take considerably longer. Arete builds these lead times into the programme from the outset, rather than treating them as a surprise later.

Do I need utility co-ordination on every highway scheme?

Not every scheme, but almost every scheme that opens up the carriageway or verge in an area with any significant buried services. The cost of a proper co-ordination workstream is a small fraction of the cost of finding an unmarked service on the day it happens.

Is utility co-ordination the same as CDM?

No. CDM governs health and safety on construction projects and sits with the Principal Designer and Principal Contractor. Utility co-ordination is a technical and commercial discipline that sits alongside CDM, feeding into it where buried services create safety risks.